It puts a lot of work ...
... the last few weeks have been very exciting and extremely busy.
I try a summary:
The upper floor is almost finished, the walls are all painted. That worked fine with the Q3 Filling deleted and the following (1 to 2 x 2x and white when color came to the wall). Except for a blanket that fewer than 5 (!) Had time to be deleted until it was finally free of streaks. In the bathroom we have used extra color (because of humidity). The floors with cork and 3-strip hardwood floor are laid. The bathroom is tiled and all the fixtures are installed. All that remains of the mirror cabinet and shower screen. If I am the door supplier can not really wait until the end of September, , the interior middle of August to be completed.
The ground floor is still not quite there yet - here is missing the floor in 2 rooms. The walls glow in white or in green (!). In the hall we have chosen a dark red color removal in - in the same color as the front door - it looks really great. Otherwise, I still
fight with the spotlights and the associated transformers - to get them into the ceiling but I have presented more easily. The guest bathroom is waiting for the Duschabtrenunng and mirror installation. The end of August comes the kitchen, but it really is all already prepared.
morning will build from Schilling nor Homeway system and some switches / sockets block - then we, the electrical fittings in the house to be finished. Outside, the wall lamps waiting to be mounted ...
The problem is waiting in the HWR: Because of the heat pump from Ehlen and from Lorenz had indeed been with us, an error in the form of a damaged O-ring was also found, however: The damn thing is already leaking somewhere. The WP will lose about 0.2 bar for 3 weeks. So the company must still ran again: Next week will be the final - which I can still see but not to this error.
to final acceptance and its preparation:
Actually, the plan - the team of FH already there - good and thorough job (thank you). Sorry, but I have a small problem (as Bianca and Christoph) - The staircase has rust in some places - in this case helps underscore unfortunately no, but only paint and the best company in earnest. Certainly a point for the final.
The wooden steps on Tuesday to lose its cardboard dress - if there are no surprises once. A small list of deficiencies still exists - but nothing dramatic. The construction supervision by me engaged the TÜV experts have complained about the fact that he has had as little to do - compliments to FH and their construction.
principle a proposal from me to FH: Is it not the home owners to send a small care set at the presentation - the remedies of the repair team have made me speechless. As quickly and thoroughly can man the plastic window (we have Foiled in dark gray) clean of the veil and plaster repair minor damage, clean the front door (wood) and polish. This is fine and easy on the nerves of the owner.
On Tuesday it will hustle and bustle - for the garage, the Tormaß taken. The garage walls are to about 2m, so that the garage until the end of August, at least a roof (though not required, the green roof) is obtained (assuming that the roofer can meet the schedule). For garden planning, I'm waiting still in the planning of ESB - whether as useful tips are included? An approximate idea of the garden I have - whether to a reasonable price can also be implemented to show the most popular. Since our construction road until next spring gives way to the finishing line, the garden is probably just a turf obtained (with a few vacancies).
to the load - the end of August - nothing stands in the way ...